The project aimed at constructing a new urban Wastewater treatment plant at Ta’ Barkat, a new Wastewater pumping station at Rinella, upgrading of the existing Xghajra pumping station, a new Wastewater gallery, and a submarine outfall. The infrastructure completed the interventions foreseen in the Sewage Master Plan and covered the remaining Wastewater discharged untreated at sea.
Project cost: € 67,966,869
Beneficiary: Water Services Corporation
Ministry: Ministry for Energy and Health
Start Date: 2009
End Date: 2012
Operational Programme: Investing in Competitiveness for a Better Quality of Life
Fund: Cohesion Fund
Focus area of intervention: Internal Mobility